62°F
weather icon Mostly Clear

1872 Mining Law clarified in Nevada; lithium mine can proceed

RENO — The Biden administration says it has completed a court-ordered review that should ensure construction continues at a Nevada lithium mine, despite legal challenges brought by conservationists and tribal leaders.

At the same time, in a broader response to recent U.S. court rulings that more strictly interpret a Civil War-era mining law, the Interior Department announced Tuesday it is taking steps to clarify mineral rights under the 1872 law to reflect the “realities of the 21st century.”

The moves come after the 9th U.S. Circuit Court of Appeals blocked a proposed copper mine in Arizona last year. The Appeals Court is considering a related appeal filed by environmentalists and Native American tribes challenging construction of the huge Thacker Pass lithium mine in Nevada near the Oregon line.

Lithium is a key element needed to manufacture batteries for electric vehicles — a centerpiece of President Joe Biden’s “clean energy” agenda intended to expedite a transition from fossil fuels to renewable forms of energy.

The 9th Circuit’s so-called “Rosemont decision” upended the government’s long-held position that the 1872 Mining Law conveys the same rights established through a valid mining claim to adjacent land for the disposal of tailings and other waste. The 9th Circuit held instead that the company must establish — and the government must validate — that valuable minerals are present under such lands for a claim to exist.

U.S. District Judge Miranda Du in Reno adopted the new standard in a ruling in February that found the U.S. Bureau of Land Management failed to comply with the law when it approved a Canadian company’s plan to open the Thacker Pass mine about 200 miles (322 kilometers) northeast of Reno.

Despite that ruling — and over the objections of environmentalists and tribes who now are appealing to the 9th Circuit — Du allowed construction to begin at the mine while the agency provides additional proof the company has the mineral rights necessary to dump waste rock and tailings from the operation on adjacent federal land.

Interior Department officials announced Tuesday that the land management bureau has completed the review necessary to establish mineral rights on the land adjacent to Lithium Americas’ project and is convinced it will satisfy Du’s requirement.

A group of Native Americans and some supporters have been staging a protest at the mine site since last week. They say federal law prohibits construction of the project near where dozens of Paiute tribal members were massacred by the U.S. cavalry in 1865.

The San Francisco-based 9th Circuit has scheduled oral arguments for the Thacker Pass appeal for June 26 in Pasadena, California.

Sen. Catherine Cortez Masto, D-Nev., called the “Rosemont decision” misguided and said it defies more than a century of practice on landscapes in the West. She recently introduced a bill with bipartisan support seeking to insulate the mine at Thacker Pass and others from the ruling by essentially adopting language that reverts to the historic interpretation that automatically conveyed established mining rights to the neighboring lands.

An Interior Department official told The Associated Press ahead of Tuesday’s formal announcement that the Biden administration doesn’t intend to challenge or appeal the Rosemont decision. The official requested anonymity because they were not authorized to discuss the issue publicly. The department issued a new legal opinion from its solicitor general to provide guidance to mining companies.

The new opinion “will support the timely review of mining proposals on federal lands and is one step of many” Interior is taking to “update guidance for mining companies to reflect the realities of the 21st century,” Deputy Interior Secretary Tommy Beaudreau said in a statement.

Dozens of other mines face similar situations as Thacker Pass, an Interior Department official said Tuesday.

“We are not appealing or challenging Rosemont,” a spokesman said. “It makes it clear for the company that if you have a situation like Rosemont or Thacker, you have these options.”

Officials analyzed more than 100 of the nearly 500 individual claims and found only eight that don’t have evidence of enough mineralization to justify siting the waste rock dump there, Interior said.

Daly reported from Washington.

Don't miss the big stories. Like us on Facebook.
THE LATEST