Experts: Challenge to build Las Vegas Raiders stadium for 2020

Updated April 1, 2017 - 11:59 pm

Southern Nevada construction industry experts say whoever ends up building the planned 65,000-seat stadium for the Las Vegas Raiders will face a massive challenge to get it done by the opening of the 2020 NFL season.

The enormity of the project, the long checklist of approvals necessary to get started and a potential labor shortage once work begins are among the roadblocks facing the Raiders, their development partner and the Las Vegas Stadium Authority.

Between today and the middle of August 2020 are 1,231 days. It took contractors working on Jerry Jones’ spectacular 80,000-seat AT&T Stadium for the Dallas Cowboys 1,346 days to complete from groundbreaking to ribbon-cutting. And three experts who have experience on projects in Southern Nevada say the Raiders will be lucky to get started within 18 months.

“With everything that has to be done, it all has to fall into place just right for it to work,” said J. Tito Tiberti, former president of J.A. Tiberti Construction, whose company has built several major projects in Southern Nevada, including 16 hotel-casinos, 20 schools and 60 water and wastewater projects.

Tiberti also is one of nine members of the Las Vegas Stadium Authority board.

“I think it’s a good 18 months of planning and permitting and I think the construction has got to take two years,” Tiberti said.

Tiberti, development consultant Gary Lake and project manager Paul Monar, who worked on a number of Marnell Corrao projects with developer Tony Marnell, talked with the Review-Journal about the challenges that await the stadium project.

Green light

The good news for the Raiders is that now that the NFL has green-lighted the team’s relocation from Oakland to Las Vegas, work can begin in earnest on multiple fronts and some of the paperwork necessary to begin moving dirt can be done simultaneously.

The Raiders won’t confirm they’ve retained architect David Manica whose Kansas City, Missouri, firm has provided a series of renderings of what the stadium could look like. Manica has an impressive resume of international stadium projects under his belt and the Raiders have posted on their website that the Las Vegas stadium would have a rigid glass-domed roof and retractable doors that would open to the north for a killer view of the Las Vegas Strip. That assumes that the Raiders purchase the 62 acres they have an option on just north of Russell Road adjacent to Interstate 15.

Now that relocation has been approved, several other stadium site pitches are expected to be made, but team executives seem firm on the Russell location.

International experience

Manica has produced designs for Reliant Stadium in Houston, a renovation for Dolphins Stadium in Miami, a concept design for Inter Milan Stadium in Italy, the Nou Camp Nou stadium renovation in Barcelona and a renovation concept for San Paolo Stadium in Naples, Italy. The firm also has been behind proposals for a Los Angeles stadium in Carson, California, an Oakland A’s baseball stadium and a combined stadium and convention center plan for the San Diego Chargers that was rejected by voters.

The Raiders still have to sign a stadium development agreement with the Las Vegas Stadium Authority, a topic that may come up at the board’s next meeting, April 20. Authority staff have said they don’t expect development and lease agreements will be ready for consideration by the nine-member board by the April or even May meetings.

The board has to be convinced that the Raiders and their development team are qualified to do the work they promise.

Big hurdles

The paperwork is only the first hurdle to clear. There are more:

■ Power. The stadium will need plenty of electricity. Where will it come from? Contractors will need to negotiate with NV Energy about utility lines, energy corridors and, possibly, substations. Tiberti said with the number of projects underway, there could be a long line at NV Energy to solve potential power problems.

■ Broadband. The ability to move data is extremely important to the NFL and it’s expected that developing the broadband to meet those needs will be a top priority. “It’s staggering to consider how much the stadium will need,” Tiberti said.

■ Drainage. Developers will be required to file plans that show the flow of water when the region gets hammered by one of those summer monsoon flash floods. Drainage studies are critical for flood control and are necessary to guarantee loans.

■ Water and sewer. Tiberti, Lake and Monar say that shouldn’t be a massive challenge, but upgrading water and sewer lines in the neighborhood surrounding the stadium may be a necessity since crews that put in existing pipes didn’t anticipate a massive stadium on that site. The fact that the primary site abuts I-15 may provide a challenge to develop sewer lines.

■ Soil studies. Developers will be required to drill 80 feet down to determine the stability of materials beneath the surface. There could be underground water; there could be unstable sand. Tiberti recalled that when Mandalay Bay — just across I-15 from the leading stadium site — was built, contractors had to shore up the building’s elevator shafts that sank an inch and threatened the building’s stability before it was shored up.

■ Traffic planning. An issue that has been raised by the Nevada Department of Transportation and the Regional Transportation Commission of Southern Nevada is to head off stadium-related traffic problems before they start. The Department of Transportation is considering moving up some already planned projects because they’d head off potential traffic woes. Among them: the redesign of the I-15-Tropicana Avenue interchange just north of the leading stadium site. Clark County Commissioner Larry Brown, who also chairs the Regional Transportation Commission, said he expects NDOT, the RTC, the Raiders and the county to discuss those issues in public forums before decisions are made.

■ Safety concerns. The Las Vegas Metropolitan Police Department and the Clark County Fire Department may need to review stadium ingress and egress to determine whether the proximity of fire stations and medical facilities are sufficient.

Near the airport

■ Once that preliminary planning is complete, construction could begin — but not before a few more details are ironed out. Because of the height of the tall cranes that will be needed for construction, developers will likely need clearance from the Federal Aviation Administration to proceed. That happened recently at Los Angeles Stadium at Hollywood Park in Inglewood, California, where the Los Angeles Rams and Chargers will play beginning in 2019. That site is close enough to Los Angeles International Airport for the FAA to review. The Las Vegas Stadium site should be close enough to McCarran International Airport for authorities to have a look.

■ The next big question for developers: Will there be enough labor available to move the project along? By the time the stadium project is ready to go, there will be other big projects underway: Project Neon. Resorts World Las Vegas. Projects at the Palms, Palace Station and Monte Carlo. The possible startup of the Las Vegas Convention Center expansion and renovation.

Workers gone

Tiberti also noted that after the Great Recession, many laborers left Southern Nevada or retired, depleting the workforce. Tiberti, Lake and Monar expect the general contractor for the project to be from out of state because they don’t believe there’s a company in Las Vegas that could handle such a project.

The stadium’s labor force will have another requirement. Within Senate Bill 1, the legislation that created the financing for the public’s $750 million contribution to the project, is a stipulation that 15 percent of the subcontracts for the project must be with small local businesses.

The contractor will have to vet small-business workforce and make sure that percentage is met.

Can the project be done on time for the 2020 season? Some of Southern Nevada’s big resort projects have been completed at remarkable paces.

Good weather

Southern Nevada has the advantage of having favorable weather to work year-round and in the hot summer months, it’s not uncommon for workers to labor in the late night and early-morning hours.

But good weather is no guarantee for a speedy project delivery. It took workers 1,208 days to complete University of Phoenix Stadium, home of the Arizona Cardinals, in 2006, yet it only took crews 963 days to finish U.S. Bank Stadium in Minneapolis in 2016.

The clock is ticking and the race is on.

Contact Richard N. Velotta at rvelotta@reviewjournal.com or 702-477-3893. Follow @RickVelotta on Twitter.

ad-high_impact_4
Business
Lehman Brothers bet big on Las Vegas
Lehman Brothers collapsed 10 years ago, helping send the country into the Great Recession.
Fremont9 opens downtown
Fremont9 apartment complex has opened in downtown Las Vegas. (Marcus Villagran/Las Vegas Review-Journal) @marcusvillagran
Ross & Snow launches in Las Vegas
Luxury shoe brand Ross & Snow has opened in Las Vegas, featuring "functional luxury" with premium shearling footwear. (Bailey Schulz/Las Vegas Review-Journal)
Remote Identification and Drones
DJI vice president of policy and public affairs discusses using remote identification on drones. (Bailey Schulz/Las Vegas Review-Journal)
Drones and public safety in Nevada
Two representatives in the drone industry discuss UAV's impact on public safety. (Bailey Schulz/Las Vegas Review-Journal)
Frontier Airlines to launch flights from Las Vegas to Mexico
Frontier, a Denver-based ultra-low-cost carrier, will become the first airline in more than a decade to offer international service to Canada and Mexico from Las Vegas when flights to Cancun and Los Cabos begin Dec. 15. (Rick Velotta/Las Vegas Review-Journal)
MGM Resorts International CEO Jim Murren addresses Oct. 1 lawsuits
MGM Resorts International Chairman and CEO Jim Murren addresses criticism his company has received for filing a lawsuit against the survivors of the Oct. 1 shooting. (K.M. Cannon/Las Vegas Review-Journal)
MGM Resorts International opens the doors on MGM Springfield
Massachusetts’ first hotel-casino opens in downtown Springfield. The $960 million MGM Springfield has 252 rooms and 125,000-square-feet of casino. (K.M. Cannon/Las Vegas Review-Journal)
MGM Resorts International prepares to open MGM Springfield
Las Vegas-based MGM Resorts International gave news media and invited guests a preview of the $960 million MGM Springfield casino in Massachusetts. The commonwealth's first resort casino will open Friday, Aug. 24. (K.M. Cannon/Las Vegas Review-Journal)
A Walk Through Circus Circus
It only takes a short walk through Circus Circus to realize it attracts a demographic like no other casino on the Strip: families with young children. (Todd Prince/Las Vegas Review-Journal)
Morphy Auctions, a vintage slot machines seller, wants gaming license
Vice president Don Grimmer talks about Morphy Auctions at the company's warehouse located at 4520 Arville Street in Las Vegas on Thursday, Aug. 16, 2018. (Rick Velotta/Las Vegas Review-Journal)
Nevada's venture capital money doesn't stay in state
Zach Miles, associate vice president for economic development for UNLV, said there’s venture money in Southern Nevada, “but trying to find the right groups to tap into for that money is different.” According to a 2017 report from the Kauffman Foundation, Las Vegas ranked number 34 out of 40 metropolitan areas for growth entrepreneurship, a metric of how much startups grow. With a lack of growing startups in Las Vegas, investment money is being sent outside of state borders. The southwest region of the U.S. received $386 million in funding in the second quarter, with about $25.2 million in Nevada. The San Francisco area alone received about $5.6 billion. (source: CB Insights)
Neon wraps can light up the night for advertising
Vinyl wrap company 5150 Wraps talks about neon wraps, a new technology that the company believes can boost advertising at night. (Marcus Villagran/Las Vegas Review-Journal) @brokejournalist
Nevada on the forefront of drone safety
Dr. Chris Walach, senior director of Nevada Institute for Autonomous Systems, talks to a reporter at NIAS's new Nevada Drone Center for Excellence of Public Safety, located inside the Switch Innevation Center in Las Vegas. K.M. Cannon Las Vegas Review-Journal @KMCannonPhoto
Motel 8 on south Strip will become site of hotel-casino
Israeli hoteliers Asher Gabay and Benny Zerah bought Motel 8 on the south Strip for $7.4 million, records show. They plan to bulldoze the property and build a hotel-casino. Motel 8 was built in the 1960s and used to be one of several roadside inns on what's now the south Strip. But it looks out of place today, dwarfed by the towering Mandalay Bay right across the street.
Project billed as one of the world's largest marijuana dispensaries plans to open Nov. 1
Planet 13 co-CEO Larry Scheffler talks about what to expect from the new marijuana dispensary, Thursday, July 19, 2018. (Marcus Villagran/Las Vegas Review-Journal) @brokejournalist
Oasis Biotech opens in Las Vegas
Brock Leach, chief operating officer of Oasis Biotech, discusses the new plant factory at its grand opening on July 18. (Bailey Schulz/Las Vegas Review-Journal)
UNLV Tech Park innovation building breaks ground
Construction on the first innovation building at the UNLV Tech Park is underway. (Bailey Schulz/Las Vegas Review-Journal)
Caesars Forum Meeting Center
Caesars broke ground Monday on its $375 million Caesars Forum Meeting Center (convention center) just east of the High Roller observation wheel. (Caesars Entertainment)
Technology reshapes the pawn shop industry
Devin Battersby attaches a black-colored device to the back of her iPhone and snaps several of the inside and outside of a Louis Vuitton wallet. The device, installed with artificial intelligence capabilities, analyzes the images using a patented microscopic technology. Within a few minutes, Battersby receives an answer on her app. The designer item is authentic.
Recreational marijuana has been legal in Nevada for one year
Exhale Nevada CEO Pete Findley talks about the one year anniversary of the legalization of recreational marijuana in Nevada. (K.M. Cannon/Las Vegas Review-Journal)
Young adults aren't saving for retirement
Financial advisors talk about saving trends among young adults. (Bailey Schulz/Las Vegas Review-Journal)
President Trump’s tariffs could raise costs for real estate developers, analysts say
President Donald Trump made his fortune in real estate, but by slapping tariffs on imports from close allies, developers in Las Vegas and other cities could get hit hard.
Las Vegas business and tariffs
Barry Yost, co-owner of Precision Tube Laser, LLC, places a metal pipe into the TruLaser Tube 5000 laser cutting machine on Wednesday, June 20, 2018, in Las Vegas. Bizuayehu Tesfaye/Las Vegas Review-Journal @bizutesfaye
Nevada Film Office Connects Businesses To Producers
The director of the Nevada Film Office discusses its revamped locations database and how it will affect local businesses. (Bailey Schulz/Las Vegas Review-Journal)
TOP NEWS
News Headlines
Add Event
Home Front Page Footer Listing
Circular
You May Like

You May Like