Water on its way from new Lake Mead straw

Take a big drink, Las Vegas. You've earned it.

As early as Friday, valley residents will get their first taste of water drawn through the Southern Nevada Water Authority's new straw at Lake Mead.

Working from a barge floating on the reservoir, contractors pulled the cap off the deep-water intake late Wednesday morning, marking substantial completion of the seven-year, $817 million project that is being paid for in part through a series of rate hikes on local water customers.

Authority officials hope to be able to put the intake into service within the next few days.

All this is coming a few weeks sooner than even the authority was expecting. As recently as Sept. 10, project officials from the authority were predicting an early October start for the new intake, which will draw from the deepest part of Lake Mead, where the coolest, cleanest water is found.

Just don't expect to taste the difference. After treatment and delivery, water pulled through the new straw will be indistinguishable from what normally flows from taps around the valley.

"It should be seamless for our customers. They shouldn't notice a difference," said Bronson Mack, spokesman for the authority.

The new intake is the most complicated and expensive project in the history of the water agency. It involved excavating a 20-foot-tall tunnel beneath the bottom of the lake and connecting it to a buried concrete intake structure poking up from the lake bed three miles from shore.

Even removing the cap from the finished structure proved tricky.

First the tunnel had to be filled with about 52 million gallons of water to equalize the pressure with the surrounding lake, a process that began two weeks ago.

Then a remote-controlled submarine was sent down into the lake to connect a cable hoist from the surface to the cap submerged 218 feet below. Once the hoist was hooked onto the 19,000-pound, 16-foot-wide disc of stainless steel, the cap was slowly lifted out of the water by the barge.

Mack said everything went off without a hitch.

The completed project is designed to provide critical drought insurance for a community that draws 90 percent of its drinking water from Lake Mead. The third intake — coupled with a $650 million pumping station due to be built over the next five years — will keep water flowing to the valley even if the lake shrinks low enough to dry out the community's two existing straws.

Construction on the intake began in 2008 and endured a series of setbacks that added more than two years and almost $40 million to the cost.

Wednesday marked the last major hurdle, though the contractor, Vegas Tunnel Constructors, is expected to remain on site through the end of the year removing equipment and finishing work on surface facilities above the intake's access shaft.

Las Vegas City Councilman and water authority board member Bob Coffin said the new intake is more than just an engineering marvel; it's "hallowed ground."

On June 11, 2012, a construction accident in the tunnel killed Thomas Albert Turner, a 44-year-old underground miner and father of two. During last week's water authority board meeting, Coffin called on everyone to remember Turner's sacrifice.

"He gave his life so all of us could have sufficient water to drink," Coffin said.

That water should be here by the weekend.

Contact Henry Brean at hbrean@reviewjournal.com or 702-383-0350. Find him on Twitter: @RefriedBrean

MOST READ
Don't miss the big stories. Like us on Facebook.
THE LATEST
Trump: Kennedy Center to close for 2 years for renovations in July

President Donald Trump said Sunday he will move to close Washington’s Kennedy Center for the Performing Arts for two years starting in July for construction.

Judge orders ICE to release 5-year-old Liam Conejo Ramos, his dad

A 5-year-old boy and his father must be released by Tuesday from the Texas center where they’ve been held after being detained by immigration officers in Minnesota, a federal judge ordered Saturday.

MORE STORIES