Vegas Nation Stadium Show host Ed Graney talks to business reporter Rick Velotta, who recently got a tour of the Las Vegas Stadium, and they go over all of the updates on the project.
Football
Nearly half of the $1.8 billion has been spent and construction on the Las Vegas stadium is about 44 percent completed with 11 of 26 canopy trusses in place.
All things considered, the Raiders’ relationship with the city and state has been a good one, and several reports Thursday enumerated some of the positives that already have emerged.
Stadium Company Chief Operating Officer Don Webb assured everyone nothing had changed on the completion date and that everything was still on schedule despite some recent snags in the delivery of steel components to the stadium site.
The third phase of PSL sales — the least expensive in the building with a range of between $500 and $3,900 per seat — are mostly in the highest levels of the stadium.
MOST READ
1
2
3
4
5
How soon could Las Vegas Valley run out of land for new homes?
‘If we win Nevada, we win the whole thing’: Trump speaks at Las Vegas rally
3 takeaways from Aces’ loss: Rookie makes first WNBA start
EDITORIAL: ‘Russian misinformation’ now evidence in Biden trial
‘It’s like a battlefield’: 15 boats burned in Lake Mead Boat Harbor fire