| WORK AREA | TRAFFIC IMPACTS | ESTIMATED DURATION & TIME FRAME |
Rancho Drive at U.S. 95 (starts Jan. 9) | Rancho Dr. reduced to 1 lane in each direction
No left turns from Rancho to U.S. 95 on-ramps
U.S. 95 northbound off-ramp closed
U.S. 95 southbound off-ramp limited to right turns only | 10 days (24-hr/days) mid-January |
|
| Rancho Drive at Bonanza Road | Rancho reduced to 1 lane in each direction
No left runs from Rancho to U.S. 95 southbound on-ramp
U.S. 95 northbound off-ramp closed
U.S. 95 southbound off-ramp limited to right turns only | 8 days (24-hr/days) late January |
|
| Rancho Drive between Bonanza Road and Washington Avenue | Rancho reduced to 2 lanes in each direction
1 additonal lane may be closed for night work
Ernest May Lane intersection open except during work in intersection | Approx. 3 weeks February |
|
| Rancho Drive at Washington Avenue | Rancho closed to thru traffic from Bonanza Road to Washington
Washington reduced to 1 lane in each direction | 1 weekend (24-hr/days) late February |
|
| Rancho Drive between Bonanza Road and Washington Avenue | Rancho reduced to 2 lanes in each direction 1 additional lane may be closed for night work | Approx. 3 weeks (night work) April |
|
| Washington Avenue eastbound lanes just west of Rancho Drive | Washington reduced to 1 lane in each direction | Approx. 3 weeks March |
|
| Washington Avenue, westbound lanes just west of Rancho Drive | Washington reduced to 1 lane in each direction | Approx. 3 weeks April |
|
| Rancho Drive at Washington Avenue | Lanes reduced on Washington and Rancho Flaggers may stop traffic | Approx. 1 week (night work) May |