The Review-Journal’s Cassie Soto and Rick Velotta talk about the roof, new seats and work to complete the 9,500-ton field tray in the Vegas Nation Stadium Show.
Search results for:
More than 2,000 laborers are at work at Allegiant Stadium where work has begun to install the translucent plastic polymer roof of the home of the Las Vegas Raiders.
Stadium company chief operating officer Don Webb remains confident Allegiant Stadium will be completed by July 31, even though the building won’t be enclosed until April.
The $2 billion Allegiant Stadium continues to be on time and on budget, even though completion of the cable net to support the translucent polymer roof won’t be completed until mid-December.
Construction crews on Thursday continued the slow process of raising a net of multi-ton steel cables that will support a translucent roof for the Raiders Allegiant Stadium.
The San Manuel Band of Mission Indians, operator of a casino property 60 miles east of Los Angeles in San Bernardino County, has signed a partnership with the Raiders.
The Las Vegas Stadium Authority approved a $90 million budget increase for Allegiant Stadium that will be used to upgrade features, enhance technology and add signage.
While it appears rigid with all its concrete and steel, Allegiant Stadium is built with flexibility to protect it from potential earthquake damage.
A highly choreographed six-week project is planned to make Allegiant Stadium an indoor venue with the installation of steel cables to support a translucent roof.
The parent company of Las Vegas-based Allegiant Air was acknowledged as the name sponsor for the $1.9 billion, 65,000-seat indoor stadium at a topping-out event Monday.